Rail Power Systems GmbH (RPS) and F&S PROZESSAUTOMATION GmbH (F&S) have assembled and completed the jointly developed compact charging substation for a charging voltage of AC 15 kV 50 Hz. Essential components, such as the medium-voltage system, the transformer, the auxiliary system and the control technology, were installed at RPS’s location in Mannheim.
The container was then transferred to F&S in Dohna near Dresden and completed there with the converter. At the end of January 2023, the container was ready for transport to Alstom in Salzgitter.
Arrival of the container at RPS’s location in Mannheim.
Completely equipped container at F&S in Dohna.