Innovative, compact, operationally flexible and inexpensive system solution used to charge battery electric multiple units (BEMU), consisting of a charging substation and overhead contact line (charging spot, spatially limited overhead contact line installation) at stations, for vehicle storage sidings and workshops. The charging substations are available for 50 Hz for nominal voltages for 15 kV and 25 kV and for 16,7 Hz at 15 kV nominal voltage. The energy for this purpose is taken from the local medium-voltage interconnected network.
The charging station consists of a charging substation and overhead contact line section for charging at a standstill or spatially limited overhead contact line installation.
The charging substation does without frequency conversion and is designed for
supply voltages. In the design of the prTS 50729, the AC 15 kV 50 Hz system voltage has been additionally specified for charging BEMU by means of current collectors at a standstill or at low speeds.
Electric vehicles for AC 15 kV 16,7 Hz can be converted in principle for operation with 50 Hz. In general, it is necessary to merely adapt the software in the vehicle’s traction control system. No hardware adjustments are necessary. The voltage level of 15 kV was selected for the reason that not all vehicles can be converted to 25 kV for insulation reasons and due to the electrical technical equipment.
A higher voltage for the charging power is a fundamental advantage, because the current at the contact point between the current collector contact strip / contact wire is the limiting quantity (80 A in accordance with EN 50367).
The charging substation for 50 Hz can be configured in two series in output ratings for 1,2 MVA (one one feeding section), 2,4 MVA (two feeding sections) or 3,6 MVA (three feeding sections) or 2,0 MVA, 4,0 MVA or 6,0 MVA. One feeding section can be loaded up to 1,2 MVA or 2,0 MVA.
Internal transport
Connecting railways
Dock railways
The balancing converter ensures symmetrical loading of the supply network, regardless of the amount of power. The balancing converter counter-acts any existing asymmetries in the supply network.
The power at each feeding section (contact line section) is variable and arbitrary. A 1,2 MVA or 2 MVA can be used for each contact line section, depending on the style. The sections do not have to be loaded evenly. Several vehicles can be charged in one section if their total output does not exceed the maximum output per feeding section. However, it is also possible to operate one contact line section alone at its maximum power.
Charging substations are set up at locations where one cannot always assume there is a particularly powerful power supply network. The network can be supported at the withdrawal point by the provision of reactive power, for example. The voltage quality can be actively improved by the converter control.
The use of power electronic components on traction units can result in circuit reactions such as harmonics and distortion reactive power. The active balancing converter can counteract this with its filter.
The balancing converter does not only ensure a symmetric power from the supply network, it can also actively reduce existing asymmetries.
The charging substation is pre-configured to meet the requirements of the operating company and delivered and installed fully equipped. Only the cables of the medium-voltage supply network and the feeding and return cables must be connected and tested, the low-voltage connection established, the container connected to earth and the protective functions tested on site. About three days are sufficient for this purpose.
Furthermore, the overhead contact line (overhead conductor rail) must be set up. Technologies like the ground shield foundation method are available for this purpose in suitable ground conditions. They allow the contact line to be set up just as quickly. The overhead contact line can be set up in the same time in parallel to the charging substation.
Railway operations are impaired only slightly or not at all during the setup due to the short set-up time.
Due to its compact style, the charging substation can be dismounted just as fast and set up elsewhere if necessary. An overhead contact line with ground shield foundation method can be dismounted completely and also reused if necessary.
Due to the prefabrication of the charging substation, merely the cable inlets and the foundations for the charging substation including an earthing system must be implemented by the customer. A level, load-bearing floor is sufficient for temporary usage.
The overhead contact line is limited, for example to the platform length, due to its style as overhead conductor rail system. Due to the rigid conductor rail, no overhead contact line area has to be assumed, which is why additional earthing measures at metal constructions are not required in this area (EN 50122-1).
Due to the overhead contact line expanding only slightly, the influence on neighbouring electrical systems such as signalling and telecommunication equipment is low and additional measures may therefore not be required. This issue must be checked and verified in individual cases.
Due to its structure, the charging power is transferred merely by the transformer. The balancing converter connected to the third winding merely has to provide the reactive balancing power, which is always lower than the charging power. The balancing converter is used less for solutions with more than one feeding sections, because these feeding sections compensate each other. The load without active intervention of the balancing converter is symmetric if three feeding sections are loaded evenly. This means that the energy efficiency increases together with the load in solutions with more than one feeding section.
In charging breaks, the balancing converter is switched off and does not cause any no-load losses itself.
The installation does not require any planning approval due to its limited size.
Transportable container solution
Main components
Protection and control
Connections required
BEMU at a standstill at platforms and/or parking facilities
Supply of spatially limited overhead contact line installations
Charging station for electrical shunters on tracks not equipped with an overhead contact line
Input
Output
TIBS®-LC3 balancing converter series
Building (up to 2,4 MVA or 4 MVA system power)
Overhead contact line design: TracFeed® OSS (overhead conductor rail system)
From planning up to implementation from a single source (charging substation and overhead contact line).
For applications for which a solution with 50 Hz is not an option, RPS and F&S offer solutions with full-scale converters within 2,5 MVA, 5 MVA or 7,5 MVA power ranges.
An example of this are the charging substations in the style for Schleswig-Holstein. These charging substations are small decentralised converter stations in terms of their design, which, however, are intended only for feeding a spatially limited overhead contact line network with a length of about 10 km.
This technology can also be used as a small substation on electrified regional lines.
Brochure:
TracFeed® BCS: Charging stations for accumulator-powered traction units
Article in eb Elektrische Bahnen, edition 121 (2023)
Charging substation with balancing converter for AC 15 kV 50 Hz put into operation
Article in eb Elektrische Bahnen, edition 120 (2022)
Cooperation project for BEMU charging station AC 15 kV 50 Hz
Article in eb Elektrische Bahnen, edition 119 (2021)
50-Hz charging stations: Concept for accumulator-powered traction units with balancing converters
Your request will be submitted both to Rail Power Systems and F&S Prozessautomation.
Our data protection regulations apply: Privacy policy
Rail Power Systems GmbH are one of the leading providers in system design and optimisation, planning, integration, implementation, maintenance and servicing of the railway infrastructure.
They provide the full range – beginning with the initial concept up to the implementation of complete solutions in the areas of system-specific design, contact lines, railway power supply, 50-Hz installations and large equipment.
Rail Power Systems GmbH
Garmischer Straße 35
81373 Munich
Germany
In the F&S Group, we are creating complex solutions together with F&S PROZESSAUTOMATION GmbH (1990) and E&A Elektrotechnik und Automatisierung GmbH (2003). F&S PROZESSAUTOMATION GmbH have been working successfully in the area of automation and control technology and power converters for over 30 years. We develop, configure, produce and supply system solutions as well as products for energy systems, supply networks and drive and processing technology.
F&S PROZESSAUTOMATION GmbH
Gewerbering 35
01809 Dohna (Dresden)
Germany